| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRE250 | CONCRETO F´C=250 KG/CM2 PREMEZCLADO | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO-01 | CONCRETO PREMEZC.RR F'C=250 KG/CM2 AGREGADO MAXIMO 3/4" (A) | M3 | 1.000000 | $1,266.00 | $1,266.00 |
| CONCRETO-05 | BOMBEO DE CONCRETO | m3 | 1.000000 | $200.00 | $200.00 |
| AGUA | Agua potable | m3 | 0.060000 | $50.00 | $3.00 |
| Suma de Material | $1,469.00 | ||||
| Mano de Obra | |||||
| CUADRILLA10 | CUADRILLA ( 1 ALBAÑIL + 5 PEONES ) | JOR | 0.040000 | $2,532.48 | $101.30 |
| Suma de Mano de Obra | $101.30 | ||||
| Equipo | |||||
| EQUIPO-005 | VIBRADOR DYNAPAC-KOHLER K-91 4 HP, LONGITUD 14 PIES | HR | 0.444400 | $25.01 | $11.11 |
| Suma de Equipo | $11.11 | ||||
| Costo Directo | $1,581.41 |