| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 54 | ZAPATA DE CIMENTACION PARA MEGAPOSTE TRONCOPIRAMIDAL DE 35.00 M. DE ALTURA, DE CONCRETO REFORZADO F´C=250 KG/CM2. BASE DE 5.00 X 5.00 M, 0.35 M DE ESPESOR CON ESCARPIO A 0.20 M, PEDESTAL DE 1.60 X 1.60 M Y CORONA DE 1.30 X 1.30 M CON ALTURA DE 2.15 M., INCLUYE ANCLAS, ACERO DE REFUERZO, CIMBRA Y CANALIZACIÓN DE PVC. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC PREM 250 3/4" | CONCRETO PREMEZC.RN F'C=250 KG/CM2 AGREGADO MAXIMO 3/4" | M3 | 12.625000 | $950.00 | $11,993.75 |
| TUBPVC | TUBERIA PVC PARA CANALIZACION | ML | 4.000000 | $90.00 | $360.00 |
| ACER3/8-1 1/2 | ACERO DE REFUERZO DE 3/8"-1 1/2" FY=4200 KG/CM2 | kg | 1,487.440000 | $8.00 | $11,899.52 |
| ALAMBRE REC#18 | ALAMBRE RECOCIDO CAL 18 | KG | 28.870000 | $17.00 | $490.79 |
| Suma de Material | $24,744.06 | ||||
| Mano de Obra | |||||
| 03 ALB+PEON | CUADRILLA OFIC ALB+PEON | jor | 10.000000 | $585.99 | $5,859.90 |
| Suma de Mano de Obra | $5,859.90 | ||||
| Auxiliar | |||||
| CIM ZAPATAS | CIMBRA EN ZAPATAS | m2 | 14.000000 | $120.40 | $1,685.60 |
| Suma de Auxiliar | $1,685.60 | ||||
| Costo Directo | $32,289.56 |