| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 97. | SUMINISTRO E INSTALACION DE VALVULA DE GLOBO DE 12”ø, EXTREMOS BRIDADOS, CLASE 300# RF, CUERPO ASTM A 216 Gr WCB, INTERIORES DE ACERO INOXIDABLE UNS S31600, VASTAGO, DISCO Y ASIENTO RECUBIERTO CON SFA 5.13 RCoCr-3, TORNILLO EXTERIOR Y YUGO, BONETE ATORNILLADO, DISCO TIPO MACHO, ASIENTO INTERCAMBIABLE, OPERADA CON VOLANTE. BS 1873 ASME B16.34, API 598, PARA SERVICIO AMARGO QUE CAUSA S.S.C. DEBE CUMPLIR CON NACE MR-01-75/ISO-15156-1 EDICIÒN 2003, DE ACUERDO AL PLANO 879-057-B1-K-023 Y ANEXO BP. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MAT-97 | VALVULA DE GLOBO DE 12"ø, EXTREMOS BRIDADOS, CLASE 300# RF, CUERPO ASTM A 216 Gr WCB, INTERIORES DE ACERO INOXIDABLE UNS S31600, VASTAGO, DISCO Y ASIENTO RECUBIERTO CON SFA 5.13 RCoCr-3, TORNILLO EXTERIOR Y YUGO, BONETE ATORNILLADO, DISCO TIPO MACHO, ASIENTO INTERCAMBIABLE, OPERADA CON VOLANTE. BS 1873 ASME B16.34, API 598, PARA SERVICIO AMARGO QUE CAUSA S.S.C. DEBE CUMPLIR CON NACE MR-01-75/ISO-15156-1 EDICIÒN 2003 | PZA | 1.000000 | $59,195.27 | $59,195.27 |
| NIT | NITROGENO | M3 | 0.001000 | $2,500.00 | $2.50 |
| Suma de Material | $59,197.77 | ||||
| Mano de Obra | |||||
| CUA28 | CUADRILLA TUBERO + AYUDANTE | JOR | 0.200000 | $1,058.98 | $211.80 |
| Suma de Mano de Obra | $211.80 | ||||
| Herramienta | |||||
| %MO02 | EQUIPO DE SEGURIDAD | (%)MO | 0.025000 | $0.00 | $0.00 |
| %MO01 | HERRAMIENTA MENOR | (%)MO | 0.025000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQCAMPLAT | EQUIPO CAMION PLATAFORMA CON GRUA HIAB DE 10 TON | HR | 0.500000 | $345.96 | $172.98 |
| EQTOR | TORQUIMETRO DE 3000 LBS MARCA TORCUP MODELO 25037 | HORA | 1.600000 | $29.21 | $46.74 |
| AME-37 | CAMION CAPACIDAD DE 3.5 TON., MARCA FORD, F-350, MODELO 2008. | HORA | 0.100000 | $199.57 | $19.96 |
| EQ-EV024 | ELEMENTOS PARA ANDAMIOS MULTIFUNCIONALES DE ALUMINIO MARCA ATLAS | HORA | 0.100000 | $19.34 | $1.93 |
| Suma de Equipo | $241.61 | ||||
| Auxiliar | |||||
| PBA94 | SUMINISTRO DE PERSONAL Y EQUIPO PARA PRUEBA HIDROSTATICA EN TUBERIAS DE ACERO AL CARBON | JOR | 0.004000 | $3,175.31 | $12.70 |
| Suma de Auxiliar | $12.70 | ||||
| Costo Directo | $59,663.87 |