| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| OBRA-EXT-10 | LOSA DE CONCRETO F'C=150 KG/CM2 TMA 3/4" EN CANAL DE ACUEDUCTO PARA FUENTE DE 6.80 X 1.00 DE 10 CM DE ESPESOR CON CIMBRA COMUN, PERDIDA, CON DESNIVEL INDICADO EN DETALLE , INCLUYE: MATERIALES, COLOCACION DE CONCRETO, REGLEADO, CURADO, DESEPERDICIS, IMPERMEABILIZANTE INTEGRAL FESTER PROP. 1KG X 50 KG DE CEMENTO, REFUERZO CON 1 VARILLA DE 3/8" A CADA 15 CM EN AMBOS SENTIDOS | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=150 H/O | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3. | 0.748000 | $663.87 | $496.57 |
| OEXTR-FESTER01 | FESTEGRAL | KG | 7.000000 | $9.80 | $68.60 |
| ACERO-01 | ACERO DEL # 3 | KG | 59.080000 | $6.00 | $354.48 |
| ACERO-02 | ALAMBRE REC. | KG | 1.780000 | $8.90 | $15.84 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 6.500000 | $6.00 | $39.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 1.700000 | $72.00 | $122.40 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.800000 | $11.00 | $8.80 |
| CIMBRA-03 | DESMOLDANTE SEPAROL DE SIKA | LT | 3.000000 | $10.00 | $30.00 |
| Suma de Material | $1,135.70 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 3.500000 | $352.18 | $1,232.63 |
| Suma de Mano de Obra | $1,232.63 | ||||
| Costo Directo | $2,368.33 |