| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 1001-41 | BANQUETA DE CONCRETO F'c=250 KG/CM2 DE 10 CM DE ESPESOR, INCLUYE CIMBRADO, ARMADO CON MALLA ELECTROSOLDADA 6-6/10-10, COLADO Y ACABADO ESCOBETEADO | M2 |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MALLA ELEC 10-10/6-6 | MALLA ELECTROSOLDADA 6-6/10-10 | M2 | 1.100000 | $10.34 | $11.37 |
| CONC PREM 250 1 | CONCRETO PREMEZCLADO F'c=250 KG/CM2 | M3 | 0.100000 | $1,182.18 | $118.22 |
| Suma de Material | $129.59 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.003000 | $290.45 | $0.87 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.030000 | $233.90 | $7.02 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.030000 | $181.41 | $5.44 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.060000 | $169.01 | $10.14 |
| Suma de Mano de Obra | $23.47 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 0.200000 | $112.45 | $22.49 |
| Suma de Auxiliar | $22.49 | ||||
| Costo Directo | $175.55 |