| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2068-17 | GABINETE DE ACERO INOXIDABLE PARA CONEXION DE SENSOR, INSTALACION CON PEDESTAL DE PTR DE 3" INCLUYE REGISTROS CONDULET, TUBERIA GALVANIZADA PARED GRUESA DE 1/2", TUBERIA LIQUATITE E INSTALACION DE CABLEADO | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| GAB AC INOX SENSOR 1 | GABINETE DE ACERO INOXIDABLE PARA SENSOR | PZA | 1.000000 | $3,255.00 | $3,255.00 |
| PTR ESTRUCTURAL 3" 1 | PTR ESTRUCTURAL DE 3" | KG | 33.000000 | $18.00 | $594.00 |
| TUBO ACERO GALV 1/2" | TUBO DE ACERO GALVANIZADO DE 1/2" | M | 4.000000 | $52.33 | $209.32 |
| TUBO LICUATITE 1/2" | TUBO DE LICUATITE DE 1/2" DE DIAMETRO | M | 2.000000 | $17.75 | $35.50 |
| SOLDADURA E-7018 1 | SOLDADURA E-7018 | KG | 3.000000 | $49.88 | $149.64 |
| PINTURA ANTICORR 1 | PINTURA ANTICORROSIVA | LTO | 0.500000 | $90.00 | $45.00 |
| PINT ESMALTE 1 | PINTURA ESMALTE | LTO | 0.500000 | $90.00 | $45.00 |
| THINER 1 | THINER PARA PINTURA EPOXIMASTIC | LTO | 0.500000 | $40.00 | $20.00 |
| MAS DESECHABLES 1 | MASCARILLA DESECHABLES | PZA | 1.000000 | $11.30 | $11.30 |
| CAP ALG PINTAR 1 | CAPUCHA DE ALGODON PARA PINTAR (SPRAY SOCK) | PZA | 1.000000 | $34.00 | $34.00 |
| LENTES DE SEG 1 | LENTE DE SEGURIDAD | PZA | 1.000000 | $46.80 | $46.80 |
| LIJA GRUESA 1 | LIJA GRUESA | PZA | 4.000000 | $11.00 | $44.00 |
| ESTOPA 2A 1 | ESTOPA SEGUNDA | KG | 1.000000 | $52.00 | $52.00 |
| PLACA DE ACERO 1/2"1 | PLACA DE ACERO DE 1/2" | KG | 10.000000 | $12.50 | $125.00 |
| TORNILLO 1/4"X1" 1 | TORNILLO DE 1/4" x 1" | PZA | 8.000000 | $4.00 | $32.00 |
| DISCO PULIDORA 1 | DISCO DE PULIDORA | PZA | 0.500000 | $68.00 | $34.00 |
| PER ANC 3/4"X 5 1/2" | PERNO ANCLA ARPON DE 3/4" x 5 1/2" | PZA | 4.000000 | $37.60 | $150.40 |
| BROCA DE 3/4" 1 | BROCA DE 3/4" | PZA | 1.000000 | $88.00 | $88.00 |
| Suma de Material | $4,970.96 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.060000 | $290.45 | $17.43 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.600000 | $233.90 | $140.34 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.600000 | $181.41 | $108.85 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.600000 | $169.01 | $101.41 |
| Suma de Mano de Obra | $368.02 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| PLANTA SOLDAR 1 | PLANTA DE SOLDAR DE GASOLINA | HORA | 4.000000 | $111.52 | $446.08 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 4.000000 | $24.34 | $97.36 |
| CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 1.000000 | $200.73 | $200.73 |
| Suma de Equipo | $744.17 | ||||
| Costo Directo | $6,083.15 |