| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| RAM | *RAMPA EN VIA PUBLICA | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | AGUA | M3 | 0.040000 | $37.70 | $1.51 |
| CONC.PREMEZ.F-C=250 | Concreto Premezclado F'c=250 Kg/cm2 T.M.A. 3/4" revenimiento tiro directo | M3 | 0.157500 | $1,000.00 | $157.50 |
| DUELA ECONOMICA 3/4" | Duela Economica 3/4" x 3 1/2" x 8 1/4' | pt | 1.050000 | $7.00 | $7.35 |
| CLAVO CON CABEZA DE | Clavo con cabeza de 3" | kg | 0.080000 | $13.05 | $1.04 |
| DIESEL | DESMOLDANTE | Lt | 0.250000 | $5.84 | $1.46 |
| MALLA LAC 6X6-6/6 | Malla lac 6x6 - 6x6 | M2 | 1.311200 | $20.00 | $26.22 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.200000 | $12.00 | $2.40 |
| ENDURECEDOR MINERAL | ENDURECEDOR MINERAL | LT | 0.187500 | $29.21 | $5.48 |
| Suma de Material | $202.96 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.166700 | $503.14 | $83.87 |
| Suma de Mano de Obra | $83.87 | ||||
| Costo Directo | $286.84 |