| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| RELL | *RELLENO NUEVO COMPACTADO EN TERRENO CON MATERIAL DE BANCO | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | AGUA | M3 | 0.030000 | $37.70 | $1.13 |
| AGUA | AGUA | M3 | 0.030000 | $37.70 | $1.13 |
| RELLENO LIMPIO | RELLENO LIMPIO | M3 | 1.300000 | $70.00 | $91.00 |
| RELLENO LIMPIO | RELLENO LIMPIO | M3 | 1.300000 | $70.00 | $91.00 |
| Suma de Material | $184.26 | ||||
| Mano de Obra | |||||
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.010000 | $197.20 | $1.97 |
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.010000 | $197.20 | $1.97 |
| Suma de Mano de Obra | $3.94 | ||||
| Equipo | |||||
| COMPACTADOR VIBRATOR | Hr. | 0.020000 | $300.00 | $6.00 | |
| COMPACTADOR VIBRATOR | Hr. | 0.020000 | $300.00 | $6.00 | |
| CARGADOR FRONTAL | CARGADOR FRONTAL | HR | 0.020000 | $387.59 | $7.75 |
| CARGADOR FRONTAL | CARGADOR FRONTAL | HR | 0.020000 | $387.59 | $7.75 |
| Suma de Equipo | $27.50 | ||||
| Costo Directo | $215.71 |