| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PLAN-5 | *PLANTILLA DE CONCRETO PREMEZCLADO F'C=100 KG/CM2 DE 5 CMS. DE ESPESOR. INCLUYE: MATERIALES, MANO DE OBRA, HERRAMIENTA Y EQUIPO. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| POLÍN 3 1/2 X 3 1/2" | Polín 3 1/2 x 3 1/2" x 8 1/4' | pt | 0.120000 | $7.50 | $0.90 |
| POLÍN 3 1/2 X 3 1/2" | Polín 3 1/2 x 3 1/2" x 8 1/4' | pt | 0.120000 | $7.50 | $0.90 |
| POLÍN 3 1/2 X 3 1/2" | Polín 3 1/2 x 3 1/2" x 8 1/4' | pt | 0.120000 | $7.50 | $0.90 |
| Suma de Material | $2.70 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.038462 | $503.14 | $19.35 |
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.038462 | $503.14 | $19.35 |
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.038462 | $503.14 | $19.35 |
| Suma de Mano de Obra | $58.06 | ||||
| Auxiliar | |||||
| CONCRETO F-C=100 H/O | Concreto 100 Kg/cm2 agregado de 38 mm, cemento normal revenimiento 8 a 10 cm. | m3 | 0.052500 | $695.15 | $36.50 |
| CONCRETO F-C=100 H/O | Concreto 100 Kg/cm2 agregado de 38 mm, cemento normal revenimiento 8 a 10 cm. | m3 | 0.052500 | $695.15 | $36.50 |
| CONCRETO F-C=100 H/O | Concreto 100 Kg/cm2 agregado de 38 mm, cemento normal revenimiento 8 a 10 cm. | m3 | 0.052500 | $695.15 | $36.50 |
| Suma de Auxiliar | $109.49 | ||||
| Costo Directo | $170.24 |