| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ESTRU-META-06 | SUMINISTRO, HABILITADO Y FABRICACION DE ARMADURAS METALICAS A BASE DE PERFILES ESTRUCTURALES (CANAL ESTRUCTURAL, PTR, PLACA); INCLUYE: MATERIALES, DESPERDICIOS, MANO DE OBRA, HERRAMIENTA Y EQUIPO. | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-ESTRUCMET-08 | CANAL CPS | KG | 0.710000 | $12.30 | $8.73 |
| CHE-ESTRUCMET-09 | PTR DE DIFERENTES MEDIDAS | KG | 0.220000 | $13.76 | $3.03 |
| CHE-ESTRUCMET-04 | PLACA A 36 | KG | 0.155000 | $13.76 | $2.13 |
| CHE-COMBUST-06 | GAS MARCA VERAGAS | KG | 0.009000 | $8.70 | $0.08 |
| CHE-COMBUST-05 | OXIGENO | M3 | 0.013000 | $52.00 | $0.68 |
| CHE-ENERGIA-02 | SUMINISTRO DE ENERGIA ELECTRICA | kw | 0.001500 | $453.00 | $0.68 |
| CHE-ESTRUC-01 | SOLDADURA E-7018 DE 1/8" | KG | 0.020000 | $52.00 | $1.04 |
| CHE-ESTRUCMET-13 | DISCO ABRASIVO | PZA | 0.002200 | $45.00 | $0.10 |
| CHE-FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.020000 | $0.00 | $0.00 |
| Suma de Material | $16.47 | ||||
| Mano de Obra | |||||
| CUADRILLA N° 341 | 1 of.pailero + 1 ayudante E. | JOR | 0.005100 | $593.32 | $3.03 |
| CUADRILLA N° 342 | 1 of.soldador + 1 ayudante E. | JOR | 0.005000 | $593.32 | $2.97 |
| CUADRILLA N° 343 | 1 of.montador + 4 ayudante A. | JOR | 0.002873 | $1,063.43 | $3.06 |
| Suma de Mano de Obra | $9.05 | ||||
| Equipo | |||||
| CHE-EQUIPO-027 | Equipo de corte de oxi-butano | HR | 0.013880 | $8.47 | $0.12 |
| CHE-EQUIPO-034 | Esmeriladora | HR | 0.028440 | $2.88 | $0.08 |
| CHE-EQUIPO-002 | SOLDADORA LINCOLN SAE 300 AMP. K 1277 MOT. PERKINS 4236, 4 CIL. 60 HP. 1600 R.P.M. | HR | 0.011440 | $8.70 | $0.10 |
| CHE-EQUIPO-036 | Grua de 20 ton. | HR | 0.003673 | $307.36 | $1.13 |
| Suma de Equipo | $1.43 | ||||
| Costo Directo | $26.94 |