| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IS-08 | SUMINISTRO Y COLOCACION DE TEE 50 MM PVC DWV C-40 INCLUYE. ACARREOS, FIJACION. NIVELACION, MATERIALES MISCELANEOS. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TEE 50MM PVC SANIT | TEE 50MM PVC SANIT | PZA | 1.000000 | $75.00 | $75.00 |
| TEE 50MM PVC SANIT | TEE 50MM PVC SANIT | PZA | 1.000000 | $75.00 | $75.00 |
| LIMPIADOR PVC | LIMPIADOR PVC | PZA | 0.050000 | $25.00 | $1.25 |
| LIMPIADOR PVC | LIMPIADOR PVC | PZA | 0.050000 | $25.00 | $1.25 |
| PEGAMENTO TANGIT | PEGAMENTO TANGIT | PZA | 0.033330 | $98.00 | $3.27 |
| PEGAMENTO TANGIT | PEGAMENTO TANGIT | PZA | 0.033330 | $98.00 | $3.27 |
| ESTOPA | ESTOPA | KG | 0.050000 | $25.00 | $1.25 |
| ESTOPA | ESTOPA | KG | 0.050000 | $25.00 | $1.25 |
| Suma de Material | $161.53 | ||||
| Mano de Obra | |||||
| CUADRILLA PLOMEROS | Cuadrilla de Plomeros | jor | 0.055560 | $413.55 | $22.98 |
| CUADRILLA PLOMEROS | Cuadrilla de Plomeros | jor | 0.055560 | $413.55 | $22.98 |
| Suma de Mano de Obra | $45.95 | ||||
| Costo Directo | $207.49 |