| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 070112 | Sobrecimiento bloque 15 | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BLOQCON15B | Bloque concreto 15x20x40 | un | 13.125000 | $1,937.00 | $25,423.13 |
| Suma de Material | $25,423.13 | ||||
| Mano de Obra | |||||
| ZCUADMAM | Cuadrilla MamposterÃa | jor | 0.069000 | $116,803.00 | $8,059.41 |
| Suma de Mano de Obra | $8,059.41 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 0.350000 | $1,000.00 | $350.00 |
| Suma de Auxiliar | $350.00 | ||||
| Concepto | |||||
| 050209 | Mortero 1: 4 de pega | m3 | 0.024000 | $285,872.00 | $6,860.93 |
| 050201 | Concreto 2000 psi en obra | m3 | 0.076000 | $261,470.00 | $19,871.72 |
| Suma de Concepto | $26,732.65 | ||||
| Costo Directo | $60,565.18 |