| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 310.1.004 | SUMINISTRO, HABILITADO, CORTES Y MONTAJE DE ESTRUCTURA METALICA PRINCIPAL , A BASE DE PERFILES IPR, IPC, LARGEROS, ANGULOS, PUNTALES, MONTEN, EN NAVE PRINCIPAL, MEZANINE OFICINAS, MEZANINE DE RECIB, VESTIBULO DE ACCESO, MARQUESINA DE ANDENES, ESCALERA DEL EDIFICIO PRINCIPAL, ESCALERA DE MEZANINE, SUBESTACIÓN ELECTRICA, CUARTO DE BOMBAS, CUERTO DE COMPRESORES, INCLUYE: MATERIALES, UNA MANO DE PRIMER ANTICORROSIVO, SOLDADURA, PRUEBAS, EQUIPO, HERRAMIENTA Y MANO DE OBRA | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| IPR DIF. MEDIDAS | KG | 0.200000 | $9.85 | $1.97 | |
| VIGA HP | KG | 0.509900 | $10.00 | $5.10 | |
| PLACA 1/4"@ 1" | KG | 0.227800 | $9.85 | $2.24 | |
| CANAL ESTRUCTURAL | KG | 0.054250 | $9.00 | $0.49 | |
| ANGULO DIF. MEDIDAS | KG | 0.054250 | $9.50 | $0.52 | |
| GAS P/ CORTES | KG | 0.009000 | $5.05 | $0.05 | |
| OXIGENO | OXIGENO | M3 | 0.008500 | $70.00 | $0.60 |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 0.007330 | $30.00 | $0.22 |
| ALAMBRE TUBULAR | KG | 0.004000 | $28.00 | $0.11 | |
| DISCO ABRASIVO | DISCO ABRASIVO | PZA | 0.002200 | $75.00 | $0.17 |
| SPOT LABORATORIO | KG | 1.000000 | $0.15 | $0.15 | |
| TORNILLERIA | TORNILLERIA | KG | 0.003600 | $60.00 | $0.22 |
| FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.021350 | $0.00 | $0.00 |
| PRIMER ESTR DUCO | LT. | 0.009600 | $47.00 | $0.45 | |
| THINER | THINER | LT | 0.076190 | $12.00 | $0.91 |
| Suma de Material | $13.19 | ||||
| Mano de Obra | |||||
| CUADRILLA N° 341 | 1 of.pailero + 1 ayudante E. | JOR | 0.002500 | $638.89 | $1.60 |
| CUADRILLA N° 342 | 1 of.soldador + 1 ayudante E. | JOR | 0.002500 | $638.89 | $1.60 |
| CUADRILLA N° 346 | 1 Maniobrista + 3 Ayudantes | JOR | 0.001667 | $1,071.88 | $1.79 |
| CUADRILLA N° 344 | 1 of.pintor + 2 ayudante A. | JOR | 0.001667 | $732.75 | $1.22 |
| Suma de Mano de Obra | $6.20 | ||||
| Equipo | |||||
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 0.013880 | $0.59 | $0.01 |
| ESMERILADORA | Esmeriladora | HR | 0.028440 | $9.24 | $0.26 |
| SOLDADORA | Soldadora Miller Mod. S64 | HR | 0.018310 | $3.75 | $0.07 |
| GRUA | Grua de 20 ton. | HR | 0.002300 | $301.42 | $0.69 |
| EQUIPO DE PINTURA | Equipo de pintura IPSA | HR | 0.035290 | $2.26 | $0.08 |
| Suma de Equipo | $1.11 | ||||
| Costo Directo | $20.50 |