| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| *TEMP17 | SUMINISTRO E INSTALACION DE SALIDA HIDRAULICA INCLUYE: TUBO DE COBRE Y CONEXIONES DE 32, 25, 19,13,HEERRAMIENTA MENOR Y MANO DE OBRA CALIFICADA. | SAL. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| INST.HIDR.T.C.008 | TUBO CU T/M 13MM | ML | 6.150000 | $19.00 | $116.85 |
| INST.HIDR.T.C.007 | TUBO CU T/M 19MM | ML | 6.150000 | $34.00 | $209.10 |
| INST.HIDR.T.C.006 | TUBO CU T/M 25MM | ML | 6.150000 | $54.00 | $332.10 |
| INST.HIDR.T.C.005 | TUBO CU T/M 32MM | ML | 6.150000 | $82.00 | $504.30 |
| INST.A.A.T.C.004 | CODO CU 90X13MM | PZA | 2.000000 | $1.95 | $3.90 |
| INST.A.A.T.C.005 | CODO CU 90X19MM | PZA | 2.000000 | $4.80 | $9.60 |
| INSTA.MIC.013 | SOLDADURA 50X50 | PZA | 0.040000 | $42.00 | $1.68 |
| INSTA.MIC.014 | PASTA FUNDENTE SILER | PZA | 0.040000 | $35.00 | $1.40 |
| INSTA.MIC.002 | ESTOPA | Kg. | 0.040000 | $13.00 | $0.52 |
| INSTA.MIC.015 | LIJA FINA ESMERIL | PZA | 0.040000 | $6.50 | $0.26 |
| INSTA.MIC.016 | GAS BUTANO | KG | 0.019000 | $7.50 | $0.14 |
| SEGUETA D/FINO | SEGUETA DIENTE FINO | PZA | 0.090909 | $7.00 | $0.64 |
| INST.A.A.T.C.006 | CODO CU 90X25MM | PZA | 1.000000 | $12.00 | $12.00 |
| INST.HIDR.T.C.011 | CODO CU 90X32MM | PZA | 1.000000 | $27.00 | $27.00 |
| TEE CU 13 MM | TEE DE COBRE DE 13 MM. MARCA IUSA | PZA | 1.000000 | $6.00 | $6.00 |
| INST.HIDR.T.C.021 | TEE DE COBRE DE 19 MM. MARCA IUSA | PZA | 1.000000 | $7.50 | $7.50 |
| INST.HIDR.T.C.020 | TEE DE COBRE DE 25 MM. MARCA IUSA | PZA | 1.000000 | $25.50 | $25.50 |
| INST.HIDR.T.C.019 | TEE DE COBRE DE 32 MM. MARCA IUSA | PZA | 1.000000 | $50.40 | $50.40 |
| INST.HIDR.T.C.033 | RED-B-19X13 CU | PZA | 1.000000 | $6.00 | $6.00 |
| INST.HIDR.T.C.031 | RED-B-25X13 CU | PZA | 1.000000 | $8.00 | $8.00 |
| INST.HIDR.T.C.027 | RED-B-32X25 CU | PZA | 1.000000 | $12.00 | $12.00 |
| INST.HIDR.T.C.030 | RED-B-25X19 CU | PZA | 1.000000 | $8.00 | $8.00 |
| INST.HIDR.T.C.028 | RED-B-32X19 CU | PZA | 1.000000 | $12.00 | $12.00 |
| INST.HIDR.T.C.029 | RED-B-32X13 CU | PZA | 1.000000 | $12.00 | $12.00 |
| Suma de Material | $1,366.89 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 32 IN | Cuadrilla de Plomeros | jor | 0.356110 | $746.78 | $265.94 |
| Suma de Mano de Obra | $265.94 | ||||
| Equipo | |||||
| SOPLETE P/GAS | EQUIPO DE GAS PARA SOLDAR, TANQUE DE 4 KG | HR | 1.230000 | $5.09 | $6.26 |
| Suma de Equipo | $6.26 | ||||
| Costo Directo | $1,639.09 |