| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IE-28-03 | SISTEMA DE ATERRIZAJE DEL CUARTO DEL SISTEMA DE VOZ Y DATOS , INLUYE : CABLE , ZAPATA, VARILLA Y REGISTROS. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MOLDE CADWELD | MOLDE CADWELD | PZA | 0.100000 | $850.00 | $85.00 |
| ZAPATA YA26-N | ZAPATA TERMINAL No. DE CATALOGO YA26-N MARCA BURNDY | PZA | 1.000000 | $73.00 | $73.00 |
| SOLDADURA 90-115 | SOLDADURA 90-115 | PZA | 1.000000 | $85.00 | $85.00 |
| VAR. COPPERWELD5/8X3 | VARILLA COPERWELD DE 5/8 X 3.00 MTS MARCA VARIT-MEX CON PROTOCOLO | PZA | 3.000000 | $170.00 | $510.00 |
| REGISTRO PREFAB 30 | REGISTRO DE CONCRETO PREFABRICADO DE 30X40X40 CM. CON TAPA DE CONCRETO | PZA | 3.000000 | $315.00 | $945.00 |
| CABLE 1/0 DESN. | LATINCASA | ML | 18.000000 | $19.30 | $347.40 |
| GEM (GAG) | GEM (GAG) | SACO | 6.000000 | $409.00 | $2,454.00 |
| CABLE CU DESNUDO 4/0 | CABLE CU DESNUDO 4/0 | ML | 12.000000 | $58.00 | $696.00 |
| Suma de Material | $5,195.40 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENS | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 1.000000 | $715.38 | $715.38 |
| Suma de Mano de Obra | $715.38 | ||||
| Costo Directo | $5,910.78 |