| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| A10-11A | REPIZON DE CONCRETO F'C=200 KG/CM2 ARMADO CON 4 VARILLAS DEL NUM. 4 Y ESTRIBOS DEL NUM. 2 A CADA 20 CM. DIMENSIONES 10x30 CM. INCLUYE: CIMBRA ARMADO Y COLADO, ACABADO PULIDO. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | AGUA | M3 | 0.060000 | $35.00 | $2.10 |
| Suma de Material | $2.10 | ||||
| Mano de Obra | |||||
| CUADRILLA NO.06 | (1 OFICIAL ALBAÑIL + 1 PEON) | JOR | 0.129200 | $621.97 | $80.36 |
| Suma de Mano de Obra | $80.36 | ||||
| Auxiliar | |||||
| ACERO REF | ACERO DE REFUERZO VARIOS DIAMETROS | TON | 0.004400 | $14,603.95 | $64.26 |
| ACERO N° 2 | acero de ref. en castillos y cadenas del no 2 (1/4"Ø) incluye: suministro y mano de obra. | kg | 0.900000 | $16.27 | $14.64 |
| CIMBRA DE MADERA | CIMBRA DE MADERA | M2 | 0.400000 | $133.08 | $53.23 |
| CONCRETO F-C=200 H/O | CONCRETO H.O. F'C=200 KG/CM2, R.N. AGR. MAX. 3/4" | M3 | 0.032000 | $964.20 | $30.85 |
| Suma de Auxiliar | $162.99 | ||||
| Costo Directo | $245.45 |