| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EQUIP-01 | COLOCACION DE UNIDAD PAQUETE DE AIRE ACONDICIONADO, INCLUYE: CHASIS DE LAMINA EN CALIBRE 18, EMPAQUES DE NEOPRENO, PIJAS DE 1/4" X 7/8", ELEVACION, MANIOBRAS, COLOCACION, FIJACION, EQUIPO, M.O., MATERIALES MISCELANEOS, (NO INCLUYE REFUERZO DE TECHUMBRE) | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TAQUETE SCI 3/8" | TAQUETE SCI 3/8" | PZA | 18.000000 | $6.60 | $118.80 |
| TORNILLO 3/8X1 1/2 | CON TUERCA Y ARANDELA | PZA | 18.000000 | $3.30 | $59.40 |
| TUERCA GALV. 3/8" | TUERCA GALV. 3/8" | PZA | 18.000000 | $0.29 | $5.22 |
| ANGULO 1 1/2" X 1/4" | ANGULO 1 1/2" X 1/4" | KG | 12.300000 | $7.50 | $92.25 |
| SOLDADURA E7018 | SOLDADURA E7018 | KG | 1.000000 | $35.00 | $35.00 |
| CHASIS DE LAMINA | CHASIS DE LAMINA CAL. 18 | PZA | 1.000000 | $3,055.52 | $3,055.52 |
| NEOPRENO 3/4" | NEOPRENO 3/4" | KG | 16.000000 | $12.30 | $196.80 |
| PIJAS 1/4" X 7/8" | PIJAS 1/4" X 7/8" | PZA | 16.000000 | $2.30 | $36.80 |
| SELLADOR PLAST | SELLADOR PLASTICEMEN | LT | 2.000000 | $65.00 | $130.00 |
| KIT DE INST MEC | KIT DE INST MEC | PZA | 1.000000 | $6,185.81 | $6,185.81 |
| Suma de Material | $9,915.60 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 18 | Cuadrilla No. 18 ( 1 Of. Fierrero + 1Ayudante). | jor | 0.800000 | $513.17 | $410.54 |
| CUADRILLA BAJA TENS | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 1.000000 | $715.38 | $715.38 |
| CUADRILLA A.A. | AIRE ACONDICIONADO | jor | 2.200000 | $1,098.82 | $2,417.40 |
| CUAD MANIOBR INST | CUAD MANIOBR INST | jor | 1.300000 | $1,249.21 | $1,623.97 |
| Suma de Mano de Obra | $5,167.29 | ||||
| Equipo | |||||
| SOLDADORA EST. | Soldadora Miller Dimension Mod. 652 | HR | 0.500000 | $31.60 | $15.80 |
| GRUAS P | 20 TON. COMPLETA | HR | 3.000000 | $452.21 | $1,356.63 |
| GRUA HIAB | Grua Tipo Hiab de 3.5 ton.Montada en camion de 10 ton | HR | 2.000000 | $373.60 | $747.20 |
| Suma de Equipo | $2,119.63 | ||||
| Costo Directo | $17,202.52 |