| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IE-06-11 | CABLE DE COBRE DESNUDO No. 2 | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CABLE CU DESN. # 2 | CABLE CU DESN. # 2 LATINCASA | ML | 1.030000 | $15.33 | $15.79 |
| MATER. MISCELANEOS | MATER. MISCELANEOS | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Material | $15.79 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENS | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.012500 | $715.38 | $8.94 |
| Suma de Mano de Obra | $8.94 | ||||
| Costo Directo | $24.73 |