| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PO-12 | SUMINISTRO Y COLOCACION DE TEE 19 MM DE DIAMETRO DE POLIPROPILENO INCLUYE: ACARREOS A UNA DISTANCIA DE 50 MTS., TRAZO, NIVELACION, MATERIALES MISCELANEOS. ANDAMIOS. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TEE 19 MM POLI | POLIPROPILENO | PZA | 1.000000 | $6.20 | $6.20 |
| TEE 19 MM POLI | POLIPROPILENO | PZA | 1.000000 | $6.20 | $6.20 |
| PINZAS TERMOFUSION | PINZAS TERMOFUSION | RENT | 0.001600 | $2,856.00 | $4.57 |
| PINZAS TERMOFUSION | PINZAS TERMOFUSION | RENT | 0.001600 | $2,856.00 | $4.57 |
| Suma de Material | $21.54 | ||||
| Mano de Obra | |||||
| CUADRILLA PLOMEROS | Cuadrilla de Plomeros | jor | 0.061000 | $723.79 | $44.15 |
| CUADRILLA PLOMEROS | Cuadrilla de Plomeros | jor | 0.061000 | $723.79 | $44.15 |
| Suma de Mano de Obra | $88.30 | ||||
| Costo Directo | $109.84 |