| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 196. | TRAZO Y NIVELACIÓN. INCLUYE: EQUIPO, HERRAMIENTA, MANO DE OBRA Y MATERIALES PARA SEÑALAMIENTOS. | m² |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ALB008 | CALHIDRA EN SACO DE 25 KG MARCA APASCO | KG | 0.005000 | $1.35 | $0.01 |
| MAD020 | BARROTE DE PINO 2 "X 4" X 10' DE 2da. | FT | 0.030000 | $12.63 | $0.38 |
| MAD006 | POLIN DE MADERA DE PINO DE 2a. DE 4" X 4". | PIEZA | 0.025000 | $18.50 | $0.46 |
| FER002 | CLAVO DE 2 1/2" A 3 1/2" MARCA HYLSA. | KG | 0.005000 | $25.97 | $0.13 |
| C032SGP | CARRETE DE HILO DE PLASTICO DE 100 METROS No. 60. | PIEZA | 0.002000 | $22.50 | $0.05 |
| ALB014 | PUENTE METALICO PARA SEÑALIZACION | PZA | 0.033333 | $46.35 | $1.54 |
| Suma de Material | $2.57 | ||||
| Mano de Obra | |||||
| CUA16 | CUADRILLA TOPOGRAFO + 4 CADENEROS | JOR | 0.002857 | $2,681.46 | $7.66 |
| CUA05 | CUADRILLA DE OBREROS | JOR | 0.002857 | $749.99 | $2.14 |
| Suma de Mano de Obra | $9.80 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)MO | 0.025000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)MO | 0.025000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AME-32 | ESTACION COMPLETA DE 6" CON ACCESORIOS COMPLETOS INCLUYE DOS GPS DE UNA BANDA PARA POSICIONAMIENTO DE VERTICES, BUILDER T200, MARCA LEICA GEOSYSTEMS, MODELO TCRA1101. | HORA | 0.022857 | $14.36 | $0.33 |
| AME-33 | NIVEL AUTOMATICO, CON TODOS SUS ACCESORIOS, RUNNER 24, MARCA LEICA GEOSYSTEMS. | HORA | 0.022857 | $9.74 | $0.22 |
| AME-37 | CAMION CAPACIDAD DE 4 TON., MARCA FORD, F-350, MODELO 2008. | HORA | 0.002000 | $202.74 | $0.41 |
| Suma de Equipo | $0.96 | ||||
| Costo Directo | $13.33 |