| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1.1.3 | COLUMNA INTERIORES DE 2.5 DE 4 m " | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| INVE03 | COLUMNA INTERIORES DE 2.5 DE 4 m " | PZ | 1.000000 | $241.36 | $241.36 |
| Suma de Material | $241.36 | ||||
| Mano de Obra | |||||
| 1I2E | CUADRILLA No 18 (1.00 OF. INST. + 2.00 AY.ESP.) | jor | 0.056290 | $728.19 | $40.99 |
| Suma de Mano de Obra | $40.99 | ||||
| Herramienta | |||||
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039OCC | FORD F-150 PICK-UP | hora | 0.005623 | $322.19 | $1.81 |
| Suma de Equipo | $1.81 | ||||
| Costo Directo | $284.16 |