| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| MEI028 | SOPORTE TRAPECIO COLGANTE PARA TUBOS O CHAROLA 30", CON VARILLA Y UNICANAL DE 0.82M DE LONGITUD | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| VARILLA ROSC. 3/8 | VARILLA ROSCADA DE 3/8" | ML | 2.500000 | $10.95 | $27.38 |
| TAQUETE SCI 3/8" | TAQUETE TIPO SCI DE 3/8" CLEVIS | PZA | 2.000000 | $3.69 | $7.38 |
| BROCA P/CONCRETO 3/8 | BROCA PARA CONCRETO DE 5/8" DE DIAMETRO X 6" DE LONGITUD Y 3/8" DE ZANCO | PZA | 0.073690 | $38.41 | $2.83 |
| TUERCA GALV. 3/8" | TUERCA GALV. 3/8" | PZA | 4.000000 | $0.36 | $1.44 |
| SEGUETA | SEGUETA | PZA | 0.030000 | $4.70 | $0.14 |
| UNICANAL U-10 | UNICANAL U-10 | ML | 0.850000 | $11.57 | $9.83 |
| TRAPECIO CLEVIS 3/8" | TRAPECIO CLEVIS 3/8" | PZA | 2.000000 | $8.05 | $16.10 |
| Suma de Material | $65.10 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.050000 | $717.17 | $35.86 |
| Suma de Mano de Obra | $35.86 | ||||
| Auxiliar | |||||
| ANDAMIO | MODULO DE 1.55 MTS PARA INSTALACIONES | R/D | 0.045800 | $28.92 | $1.32 |
| Suma de Auxiliar | $1.32 | ||||
| Costo Directo | $102.28 |