| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 16 | TRAZO Y NIVELACIÓN CON EQUIPO TOPOGRÁFICO, PARA DESPLANTE DE ESTRUCTURAS. | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PGPB-T1-MAD-01 | BARROTE 1.75" X 3 1/2" X 8 | pt | 0.027000 | $7.22 | $0.19 |
| PGPB-T1-MAD-02 | DUELA DE 1" X 4" X 8 | pt | 0.018000 | $8.75 | $0.16 |
| PGPB-T1-PINT-01 | Pintura esmalte | lt | 0.002193 | $71.73 | $0.16 |
| PGPB-T1-OT-04 | Hilo plastico | ml | 0.350000 | $1.13 | $0.40 |
| PGPB-T1-AGLU-01 | Calhidra | kg | 0.250000 | $1.56 | $0.39 |
| Suma de Material | $1.30 | ||||
| Mano de Obra | |||||
| PGPB-T2-C12 | Cuadrilla no. 12 (1 topógrafo + 3 ayudantes) | jor | 0.003226 | $2,110.10 | $6.81 |
| Suma de Mano de Obra | $6.81 | ||||
| Herramienta | |||||
| %MO01 | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| %MO02 | Equipo de Primera Seguridad (Casco, Botas, Guantes, Gafas, Chaleco Preventivo) | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| PGPB-T4-16 | Auxiliar de equipo No. 16 (Equipo topografico estacion totaI, 8 hr + Camioneta de 3 ton redilas, 1 hr) | jor | 0.003226 | $735.56 | $2.37 |
| Suma de Auxiliar | $2.37 | ||||
| Costo Directo | $10.48 |