| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| MG126 | COPLE TAR 50MM | Pza. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| COPLE TAR 50 MM | COPLE TAR 50 MM | PZA | 1.000000 | $18.65 | $18.65 |
| COPLE TAR 50 MM | COPLE TAR 50 MM | PZA | 1.000000 | $18.65 | $18.65 |
| Suma de Material | $37.30 | ||||
| Mano de Obra | |||||
| CUADRILLA PLOMEROS | Cuadrilla de Plomeros | jor | 0.011111 | $733.26 | $8.15 |
| CUADRILLA PLOMEROS | Cuadrilla de Plomeros | jor | 0.011111 | $733.26 | $8.15 |
| Suma de Mano de Obra | $16.29 | ||||
| Auxiliar | |||||
| ANDAMIO | MODULO DE 1.55 MTS PARA INSTALACIONES | R/D | 0.011110 | $50.40 | $0.56 |
| ANDAMIO | MODULO DE 1.55 MTS PARA INSTALACIONES | R/D | 0.011110 | $50.40 | $0.56 |
| Suma de Auxiliar | $1.12 | ||||
| Costo Directo | $54.71 |