| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 31.03 | 25 MM DE DIAMERTO | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PINTURA SHERWIN | PINTURA ESMALTE SHERWIN WILLIAMS | LT | 0.031350 | $73.04 | $2.29 |
| THINER | THINER | LTO | 0.015170 | $14.50 | $0.22 |
| ESTOPA | ESTOPA | Kg. | 0.032000 | $25.00 | $0.80 |
| Suma de Material | $3.31 | ||||
| Mano de Obra | |||||
| CUADRILLA NO 11 INST | PINTURA EN TUBERIA TANQUES Y EQUIPOS | JOR | 0.010357 | $437.21 | $4.53 |
| Suma de Mano de Obra | $4.53 | ||||
| Costo Directo | $7.84 |