| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4.01 | 51 x 38 mm DE DIAMETRO FIG. 701-2-R | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| REDBUSCUS51X38 | REDUCCION BUSHIGN DE COBRE SOLDABLE DE 51 A 38MM | PZA | 1.000000 | $59.16 | $59.16 |
| CONECCUR/INT13 | CONECTOR DE COBRE ROSCA INTERIOR 13MM | PZA | 1.000000 | $10.10 | $10.10 |
| SOLDADURA 50X50 | SOLDADURA 50X50 | PZA | 0.003710 | $35.00 | $0.13 |
| SOLDADURA PLATA | SOLDADURA PLATA | KG | 0.008400 | $2,500.00 | $21.00 |
| PASTA FUNDENTE SILER | PASTA FUNDENTE SILER | PZA | 0.002270 | $22.00 | $0.05 |
| SIMPLE GREEN | SIMPLE GREEN | LT | 0.054680 | $82.30 | $4.50 |
| INS LIJA FINA ESM | LIJA FINA ESMERIL | PZA | 0.013740 | $8.73 | $0.12 |
| AGUA | AGUA ACARREO INTERNO | M3 | 0.060000 | $30.00 | $1.80 |
| Suma de Material | $96.86 | ||||
| Mano de Obra | |||||
| CUAD OC 13 | CUADRILLA DE PLOMEROS | JOR | 0.003100 | $697.14 | $2.16 |
| CUAD INST ESPECIAL | CUADRILLA DE INSTALACIONES ESPECIALES | JOR | 0.011830 | $1,822.48 | $21.56 |
| Suma de Mano de Obra | $23.72 | ||||
| Equipo | |||||
| SOPLETE P/GAS | EQUIPO DE GAS PARA SOLDAR, TANQUE DE 4 KG | HR | 0.093700 | $13.66 | $1.28 |
| EQAOX001 | EQUIPO DE OXIACETILENO | HR | 0.016320 | $63.93 | $1.04 |
| Suma de Equipo | $2.32 | ||||
| Auxiliar | |||||
| ANDAMIO | MODULO DE 1.55 MTS PARA INSTALACIONES | R/D | 0.602070 | $15.48 | $9.32 |
| Suma de Auxiliar | $9.32 | ||||
| Costo Directo | $132.22 |