| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.16 | SUMINISTRO Y FABRICACION DE BASE DE CONCRETO F'C= 250 Kg/cm2, DE SECCION TRONCOPIRAMIDAL, PARA SOPORTE DE POSTE DE ALUMBRADO, CON BASE INFERIOR DE 60X60 CM, BASE SUPERIOR DE 40X40 CM Y ALTURA DE 100 CMS. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO VARIOS DIAM | ACERO DEL # 3 ( 3/8") AL # 12 (1 1/2") | KG | 9.000000 | $9.00 | $81.00 |
| ALAMBRE | ALAMBRE RECOCIDO | KG | 1.500000 | $11.00 | $16.50 |
| CIMBRA-001 | CIMBRAPLAY 16 MM HOJA DE 1.22 X 2.44 | M2 | 1.000000 | $97.00 | $97.00 |
| CIMBRA05 | CLAVO (VARIAS MED.) | Kg | 1.500000 | $12.50 | $18.75 |
| CIMBRA-04 | MADERA DE PINO | PT | 4.000000 | $7.00 | $28.00 |
| DIESEL | Diesel | LT | 2.000000 | $5.20 | $10.40 |
| CONCRETO PRE-05 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2, ELABORADO CON CEMENTO CPO-30-RS | M3 | 0.500000 | $986.70 | $493.35 |
| Suma de Material | $745.00 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 1.560000 | $778.44 | $1,214.37 |
| Suma de Mano de Obra | $1,214.37 | ||||
| Equipo | |||||
| AMAQUINARIA-23 | VIBRADOR PARA CONCRETO MCA CIPSA CON MOTOR KOHLER 4 H.P. CONJUNTO CABEZAL DE 14" | HR | 0.500000 | $48.82 | $24.41 |
| Suma de Equipo | $24.41 | ||||
| Costo Directo | $1,983.78 |