| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 65 | ESPECIFICACIÓN PARTICULAR No. 27 | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MA227 | Pegamento Para Tuberia De Pvc | LT | 0.050000 | $95.00 | $4.75 |
| MA015 | Agua Limpia | M3 | 0.001960 | $62.50 | $0.12 |
| MA346 | Tuberia Sanitaria De Pvc De 50 Mm Ø | M | 1.050000 | $9.88 | $10.37 |
| MA197 | Lija Grano Grueso | PZA | 0.050000 | $3.59 | $0.18 |
| Suma de Material | $15.43 | ||||
| Mano de Obra | |||||
| CUADFONTANERO | Mano De Obra: 1 Oficial Fontanero + 2 Ay | JORN | 0.033333 | $1,772.17 | $59.07 |
| Suma de Mano de Obra | $59.07 | ||||
| Equipo | |||||
| %MOHM | Herramienta menor | (%)MO | 0.020000 | $0.00 | $0.00 |
| BEQUI-AND010 | Equipo: Andamios Tubulares Y Escaleras | HR | 0.333333 | $0.00 | $0.00 |
| BEQUI-CAM80 | Equipo: Camion 3 Ton Redilas | HR | 0.005556 | $119.85 | $0.67 |
| BEQUI-BOMEMB | Equipo: Bomba De Embolo Manual 3/4 | HR | 0.050000 | $0.00 | $0.00 |
| %MOES | Equipo de Seguridad Personal | (%)MO | 0.050000 | $0.00 | $0.00 |
| Suma de Equipo | $0.67 | ||||
| Costo Directo | $75.16 |