| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRETO 250 3/4" | CONCRETO Fc= 250 KG/CM2, RESISTENCIA NORMAL, T.M.A. 19 mm HECHO EN OBRA | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| GRAVA DE 3/4" | GRAVA DE 3/4" | M3 | 0.700000 | $200.00 | $140.00 |
| CEMENTO GRIS | CEMENTO GRIS | TON | 0.430000 | $1,500.00 | $645.00 |
| ARENA | ARENA | M3 | 0.500000 | $90.00 | $45.00 |
| AGUA | AGUA | M3 | 0.250000 | $50.00 | $12.50 |
| Suma de Material | $842.50 | ||||
| Costo Directo | $842.50 |