| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 67 | 150 | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MA344 | Tuberia Sanitaria De Pvc De 150 Mm Ø | M | 1.050000 | $60.00 | $63.00 |
| MA015 | Agua Limpia | M3 | 0.017700 | $62.50 | $1.11 |
| MA227 | Pegamento Para Tuberia De Pvc | LT | 0.020000 | $95.00 | $1.90 |
| MA197 | Lija Grano Grueso | PZA | 0.100000 | $3.59 | $0.36 |
| Suma de Material | $66.37 | ||||
| Mano de Obra | |||||
| CUADFONTANERO | Mano De Obra: 1 Oficial Fontanero + 2 Ay | JORN | 0.050000 | $1,772.17 | $88.61 |
| Suma de Mano de Obra | $88.61 | ||||
| Equipo | |||||
| BEQUI-AND010 | Equipo: Andamios Tubulares Y Escaleras | HR | 0.333333 | $0.00 | $0.00 |
| %MOHM | Herramienta menor | (%)MO | 0.020000 | $0.00 | $0.00 |
| %MOES | Equipo de Seguridad Personal | (%)MO | 0.050000 | $0.00 | $0.00 |
| BEQUI-BOMEMB | Equipo: Bomba De Embolo Manual 3/4 | HR | 0.055556 | $0.00 | $0.00 |
| Suma de Equipo | $0.00 | ||||
| Costo Directo | $154.97 |