| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1.38 | PERFILADO DE ARISTAS VIVAS CON MORTERO CEMENTO ARENA 1:5, INCLUYE: MATERIALES Y MANO DE OBRA. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA-3 | MADERA DE PINO DE 3A. EN POLIN DE 4" X 4" | PT | 0.300000 | $7.50 | $2.25 |
| AGUA | ACARREO INTERNO | M3 | 0.020000 | $40.00 | $0.80 |
| Suma de Material | $3.05 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.035714 | $644.92 | $23.03 |
| Suma de Mano de Obra | $23.03 | ||||
| Herramienta | |||||
| ANDAMIOS | ANDAMIOS | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| MORTERO CEM-ARE 1:4 | Mortero cemento arena 1 : 4 | M3 | 0.003000 | $920.21 | $2.76 |
| Suma de Auxiliar | $2.76 | ||||
| Costo Directo | $28.84 |