| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| UV 2201 | CELOSÍA DE CEMENTO DE 20X20 CM. ASENTADA CON MORTERO CEMENTO ARENA 1:4, INCLUYE MATERIALES, MANO DE OBRA, HERRAMIENTA EQUIPO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN (P.U.O.T.) | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CELOSIA 20X20X8 | CELOSIA 20X20X8 | M2 | 1.100000 | $130.50 | $143.55 |
| AGREGADO-003 | AGUA | M3 | 0.060000 | $30.00 | $1.80 |
| Suma de Material | $145.35 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.111111 | $634.95 | $70.55 |
| Suma de Mano de Obra | $70.55 | ||||
| Herramienta | |||||
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.150000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| MORTERO CEM-ARE 1:4 | Mortero cemento arena 1 : 4 | M3 | 0.023400 | $987.28 | $23.10 |
| Suma de Auxiliar | $23.10 | ||||
| Costo Directo | $239.00 |