| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| NVL2-16 | " FABRICACION DE ESTRUCTURA DE ACERO ESTRUCTURAL (VI-5) FORMADA CON PERFILES PESADOS IPC CON MEDIDAS DE 533 X 305 MM PESO DE (92.9 KG/ ML) .HASTA UNA ALTURA DE 5.50 MTS, (SEGUNDO NIVEL) INCLUYE RIGIDIZADOR DE ALMA DE 1/4"" @ 1.10 MTS, CONEXIONES P.U.O.T. " | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| IPR 18"X96.90 | VIGA IPC A-36 21" x 12" 92.90 KG/ML | kg | 1.120000 | $13.85 | $15.51 |
| FLETE | FLETE DEL TALLER DE ESTRUCTURAS A LA OBRA | kg | 1.000000 | $0.50 | $0.50 |
| Suma de Material | $16.01 | ||||
| Mano de Obra | |||||
| A02-1510 | CUADRILLA No. 151 (PARA FABRICACION DE ESTRUCTURA METALICA.) | jor | 0.000870 | $7,448.11 | $6.48 |
| A02-1520 | CUADRILLA No. 152 (PARA MONTAJE DE ESTRUCTURA METALICA) | jor | 0.000833 | $5,909.20 | $4.92 |
| Suma de Mano de Obra | $11.40 | ||||
| Herramienta | |||||
| 00-0009 | CONSUMOS DE FABRICACION EN ESTRUCTURA METALICA | (%)m | 0.060000 | $0.00 | $0.00 |
| 00-0007 | CONSUMOS DE MONTAJE EN ESTRUCTURA METALICA | (%)m | 0.060000 | $0.00 | $0.00 |
| 00-0005 | CONTROL DE CALIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| 0RESOLDADORA | Soldadora Miller Mod. S64 | HR | 0.030000 | $9.20 | $0.28 |
| 03-8070 | METALERO | hora | 0.006000 | $11.59 | $0.07 |
| 0EQUIPO DE CORTE | Equipo de corte de oxi-butano | hora | 0.008700 | $8.47 | $0.07 |
| 03-8050 | GRUA VIAJERA | hora | 0.000450 | $20.92 | $0.01 |
| 03-6050 | GRUA PETTIBONE 25,000 LBS. | hora | 0.000400 | $1,222.75 | $0.49 |
| 03-6051 | GRUA P&H DE 75 TON. | hora | 0.000667 | $1,357.71 | $0.91 |
| Suma de Equipo | $1.82 | ||||
| Costo Directo | $29.24 |