| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 090305 | Subbase granular | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SUBBASE02 | Subbase granular | m3 | 1.350000 | $19,549.00 | $26,391.15 |
| Suma de Material | $26,391.15 | ||||
| Mano de Obra | |||||
| AYUDRAS | Ayudante Raso | jor | 0.055560 | $30,212.00 | $1,678.58 |
| Suma de Mano de Obra | $1,678.58 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MOTON | Motoniveladora | hr | 0.066667 | $100,000.00 | $6,666.70 |
| COMPACT25 | Compactador vibratorio | hr | 0.066667 | $100,000.00 | $6,666.70 |
| TANQU | Tanque para riego | hr | 0.066667 | $3,227.00 | $215.13 |
| Suma de Equipo | $13,548.53 | ||||
| Auxiliar | |||||
| TRZAGR20 | Transporte pétreos | m3 | 1.350000 | $20,571.00 | $27,770.85 |
| Suma de Auxiliar | $27,770.85 | ||||
| Concepto | |||||
| 020209 | Perfilacion y compactacion de sub-rasante. | m2 | 0.500000 | $5,903.00 | $2,951.50 |
| Suma de Concepto | $2,951.50 | ||||
| Costo Directo | $72,340.61 |