| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 02-090-160 | MESETA DE CONCRETO F'C=200 KG/CM2 DE 5 CMS. DE ESPESOR, REFORZADO CON MALLALAC 6X6 6/6 ANCLADA A CADENA DE CONCRETO F'C=200 KG/CM2, ARMADA CON VARILLA DEL #3, FORRADA CON LOSETA CERAMICA CREMO MARFIL.(VER ESP. HTT 02-050, HTT 04-070) | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MALLA ELECT 6X6-6/6 | Malla electrosoldada 66-66 (2.05 kg/m2). | m2 | 1.100000 | $27.50 | $30.25 |
| ADHESIVO INTERCER. | Adhesivo porcelanico, contenido 20 kg x saco, marca interceramic | saco | 0.400000 | $127.00 | $50.80 |
| BOQUILLA INTERCRAMIC | BOQUILLA INTERCRAMIC | KG | 2.000000 | $18.00 | $36.00 |
| MADERA PINO 3A | MADERA PINO 3A DIFERENTES DIMENSIONES | pt | 2.850000 | $7.75 | $22.09 |
| CIMBRAPLAY 16MM. | CIMBRAPLAY 16MM. | M2 | 0.200000 | $115.00 | $23.00 |
| CLAVO DIF. MEDIDAS | CLAVO DIFERENTES MEDIDAS | KG | 0.250000 | $17.00 | $4.25 |
| ALAMBRE RECOCIDO. | ALAMBRE RECOCIDO. | KG | 0.150000 | $13.00 | $1.95 |
| LOSETA 40X40 CREMA M | LOSETA 40X40 CM. INERCERAMIC CREMA MARFIL | m2 | 1.100000 | $175.00 | $192.50 |
| Suma de Material | $360.84 | ||||
| Mano de Obra | |||||
| CUADRILLA 002 VANG | Cuadrilla No 2 (1 Albañíl + 1.00 Ayudante) | JOR | 0.200000 | $962.82 | $192.56 |
| CUADRILLA 011 VANG | Cuadrilla No 11 ( 1 AZULEJERO + 1 AYUDANTE DE AZULEJERO ) | JOR | 0.200000 | $1,027.61 | $205.52 |
| Suma de Mano de Obra | $398.09 | ||||
| Auxiliar | |||||
| CONC HO FC=200 | Concreto 200 Kg/cm2 hecho en obra, agregado de 19mm, cemento normal revenimiento 8 a 10 cm. | m3 | 0.053600 | $1,207.20 | $64.71 |
| Suma de Auxiliar | $64.71 | ||||
| Concepto | |||||
| 02-070-121 | CADENA DE CERRAMIENTO CD-01 SECCION 12 X 20 CM. CONCRETO RESISTENCIA NORMAL F'C=250 KG/CM2 T.M.A. 3/4" HECHO EN OBRA, ARMADO CON ACERO DE REFUERZO 4 ø DEL No.3 (3/8") ESTRIBOS DEL No. 2 (1/4")@ 20 CMS, CIMBRA COMUN.(VER ESP HTT 02-020) | ML | 0.700000 | $230.49 | $161.34 |
| Suma de Concepto | $161.34 | ||||
| Costo Directo | $984.97 |