| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| UV-302 | ACABADO MARTELINADO SOBRE FIRME DE CONCRETO (VER PLANO DP-01) INCLUYE: MATERIALES, MANO DE OBRA, HERRAMIENTA, EQUIPO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION (P.U.O.T.) | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| FESTERBOND | FESTERBOND | LT | 0.020000 | $34.42 | $0.69 |
| Suma de Material | $0.69 | ||||
| Mano de Obra | |||||
| CUADRILLA 09 | (1 OF. ALBAÑIL + 1 PEON) | jor | 0.055556 | $696.36 | $38.69 |
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.333333 | $285.16 | $95.05 |
| Suma de Mano de Obra | $133.74 | ||||
| Auxiliar | |||||
| CONCRETO GR.MARM.200 | CONCRETO GR.MARM.200 | M3 | 0.050000 | $2,159.19 | $107.96 |
| Suma de Auxiliar | $107.96 | ||||
| Costo Directo | $242.39 |