| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2000.01.3 | SUMINISTRO Y COLOCACION DE MATERIALES PARA LA TRANSICION AEREA-SUBTERRANEA DEL ANILLO EXCLUSIVO PARA LA PLZA CON POSTE PC-13-600, INCLUYE: POSTE, APARTARRAYOS, CORTACIRCUITOS, YUGO DE MADERA, CONECTORES PERICO Y ESTRIBO, 3-TUBO PAD-RD35 DE 76mm, 3-CABLE DE ENERGIA XLP-25KV CAL 1/0, TERMINAL TERMOCONTRACTIL TIPO EXTERIOR 3M,E INTERIOR, INSERTO BUSHING, CODO DE OPERACION CON Y SIN CARGA, EXCAVACION Y RELLENO, Y TODO LO NECESARIO PARA SU BUEN FUNCIONAMIENTO A UNA DISTANCIA APROX DE 45 MTS | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO C.G.P.G 101MM | TUBO C.G.P.G 101MM | ML | 198.000000 | $75.00 | $14,850.00 |
| MADERA DE PINO DE 3A | MADERA DE PINO DE 3a. | PT | 5.000000 | $9.60 | $48.00 |
| SEPARADOR | SEPARADOR | PZA | 45.000000 | $15.00 | $675.00 |
| CABLE XLP 1/0 AL25KV | CABLE XLP 1/0 AL25KV LATINCASA | ML | 245.000000 | $107.00 | $26,215.00 |
| CRUCETA C4R | CRUCETA C4R | PZA | 1.000000 | $350.00 | $350.00 |
| CORTA CIRC.SMD-20 | CORTA CIRC.SMD-20 | PZA | 6.000000 | $3,200.00 | $19,200.00 |
| TERM. COD 15KV 3/0 | TERM. COD 15KV 3/0 | PZA | 6.000000 | $3,250.00 | $19,500.00 |
| AISLADOR CT4 | AISLADOR CT4 | PZA | 3.000000 | $88.00 | $264.00 |
| APARTARRAYO 30KV | APARTARRAYO 30KV | PZA | 3.000000 | $650.00 | $1,950.00 |
| CABLE CU DESN. 2 | CABLE CU DESN. 2 | ML | 48.300000 | $20.32 | $981.46 |
| ABRAZADERA 2U | ABRAZADERA 2U | PZA | 2.000000 | $45.00 | $90.00 |
| CARGA CADWELD 4/0 | CARGA CADWELD 4/0 | PZA | 8.000000 | $185.00 | $1,480.00 |
| VARILLA COPP. 5/8X3M | MAT. | PZA | 4.000000 | $140.00 | $560.00 |
| CONECTOR. GAR | CONECTOR. GAR | PZA | 4.000000 | $350.00 | $1,400.00 |
| ELEMENTO P/FIJACION | ELEMENTO P/FIJACION | JGO. | 10.000000 | $8.50 | $85.00 |
| BASE 13 TERMINALES | BASE 13 TERMINALES | PZA | 1.000000 | $3,856.00 | $3,856.00 |
| CAJA CONEX.200 A. | CAJA CONEX.200 A. | PZA | 1.000000 | $3,050.00 | $3,050.00 |
| ELEMENTO P/FIJACION | ELEMENTO P/FIJACION | JGO. | 16.000000 | $8.50 | $136.00 |
| POSTE | POSTE PC-13-600 | PZA | 1.000000 | $2,850.00 | $2,850.00 |
| CODO 15 KV ELASTIMOL | CODO 15 KV ELASTIMOL | PZA | 3.000000 | $430.00 | $1,290.00 |
| INSERTO 15 KV | INSERTO | PZA | 3.000000 | $430.00 | $1,290.00 |
| TUBO DE PVC PESA 3 " | TUBO PAD-RD35 | ML | 18.000000 | $38.00 | $684.00 |
| EX000100 | EXCAVACION A MANO EN CEPAS HASTA 2.00 M DE PROFUNDIDAD, EN MATERIAL I, INCLUYE AFINE DE TALUDES Y FONDO SIN INCLUIR ACARREOS. | M3 | 35.250000 | $80.00 | $2,820.00 |
| CONECT. 4/0 BURDY | CONECT. 4/0 BURDY | PZA | 13.000000 | $112.00 | $1,456.00 |
| TAPA C.F.E. | TAPA CON LEYENDA C.F.E. | PZA | 2.000000 | $1,825.00 | $3,650.00 |
| Suma de Material | $108,730.46 | ||||
| Mano de Obra | |||||
| CUADRILLA -03 | (1 OFICIAL ALBAÑIL + 5 AYUDANTES). | JOR | 5.000000 | $1,555.10 | $7,775.50 |
| CUADRILLA BAJA TENS | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 6.000000 | $730.29 | $4,381.74 |
| CUADRILLA BAJA TENS | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 8.000000 | $730.29 | $5,842.32 |
| CUADRILLA -02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 4.500000 | $667.26 | $3,002.67 |
| Suma de Mano de Obra | $21,002.23 | ||||
| Equipo | |||||
| GRUAS 20 TON | 20 TON. COMPLETA | HR | 8.000000 | $529.26 | $4,234.08 |
| Suma de Equipo | $4,234.08 | ||||
| Auxiliar | |||||
| CONCTO F-C=150 IN | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3. | 1.000000 | $310.68 | $310.68 |
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra, resistencia normal, T.M.A. 3/4" | M3 | 4.000000 | $699.12 | $2,796.48 |
| Suma de Auxiliar | $3,107.16 | ||||
| Concepto | |||||
| EXT.17. | ACERO DE REFUERZO DE VARIOS DIAMETROS PARA COLUMNAS FC = 4200 KG/CM2 EN COLUMNAS DE CONCRETO INCLUYE : HABILITADO Y ARMADO , MATERIAL, MANO DE OBRA HERRAMIENTAS Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION . | ton | 0.350000 | $10,847.00 | $3,796.45 |
| Suma de Concepto | $3,796.45 | ||||
| Costo Directo | $140,870.38 |