| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| B-4 | FIRME DE CONCRETO DE 12 CM. DE ESPESOR REF. CON MALLA 6X6-10/10. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO-001 | CONCRETO PREMEZCLADO F'C=250 10-13 | M3 | 0.125000 | $970.00 | $121.25 |
| ACERO-MALLA-01 | MALLA ELECTROSOLDADA 6-6 /4-4 | M2 | 1.100000 | $23.80 | $26.18 |
| ACERO-ALAMBRE-01 | ALAMBRE RECOCIDO CAL. 18 | KG | 0.010000 | $10.63 | $0.11 |
| ACERO VARIOS | ACERO DE REFUERZO DE DIFERENTES DIAMETROS | KG | 0.200000 | $8.50 | $1.70 |
| CIMBRAMETALICA | CIMBRA METALICA(CANAL MONTEN) | ML | 0.014300 | $80.10 | $1.15 |
| AGREGADO-003 | AGUA ACARREO INTERNO | M3 | 0.021000 | $40.00 | $0.84 |
| Suma de Material | $151.22 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 03 | (1 Of. Albanil + 5 Peones). | JOR | 0.023000 | $2,049.21 | $47.13 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1 Ayud.) | jor | 0.005500 | $686.27 | $3.77 |
| Suma de Mano de Obra | $50.91 | ||||
| Equipo | |||||
| REGLA VIBRATORIA | REGLA VIBRATORIA | hora | 0.003571 | $194.64 | $0.70 |
| ALLANADORA MECANIC. | ALLANADORA MECANICA CON ASPAS | hora | 0.015000 | $222.35 | $3.34 |
| Suma de Equipo | $4.03 | ||||
| Costo Directo | $206.16 |