| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 450 | GUARNICION DE CONCRETO DE 10 X 10 CMS. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| DESMOLDANTE | DESMOLDANTE | LT | 0.500000 | $13.80 | $6.90 |
| ACE#3 | ACERO DE REFUERZO DE 3/8" #3 f`y = 4200 kg/ml | KG | 3.280000 | $8.20 | $26.90 |
| ACE#4 | ACERO DE REFUERZO De 1/2" #4 f`y = 4200 kg/ml | kg | 4.100000 | $8.20 | $33.62 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.300000 | $12.00 | $3.60 |
| CONC.PREMEZ.F-C=200 | CONCRETO PREMEZCLADO F'C= 200 KG/CM2 | M3 | 0.011000 | $991.90 | $10.91 |
| Suma de Material | $81.93 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.070000 | $764.36 | $53.51 |
| Suma de Mano de Obra | $53.51 | ||||
| Auxiliar | |||||
| BAS -CIMMET | CIMBRA METALICA DE 40 CMS DE ALTURA | ml | 0.020000 | $557.32 | $11.15 |
| Suma de Auxiliar | $11.15 | ||||
| Costo Directo | $146.58 |