| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 611 | SUMINISTRO Y COLOCACION DE BARANDAL PARA COLOCACION DE CARRITOS EN EL AREA DEL ESTACIONAMIENTO A BASE DE TUBO GALVANIZADO DE 2" DE DIAMETRO, CED. 40 ALTURA H=0.90m CON CIMENTACION PARA CADA POSTE (16 POSTES EN TOTAL) DE CONCRETO ARMADO DE 0.20M x | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO GALV 2" | TUBO GALV. 2" CEDULA 40 | ML | 32.000000 | $105.00 | $3,360.00 |
| TUBO GALV 1" | TUBO GALV. 1" CEDULA 40 | ML | 32.000000 | $70.00 | $2,240.00 |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 6.000000 | $30.00 | $180.00 |
| COMBUSTIBLE 06 | GAS P/ CORTES | KG | 10.000000 | $4.05 | $40.50 |
| COMBUSTIBLE 07 | OXIGENO | M3 | 6.000000 | $40.00 | $240.00 |
| DISCO P/DESVASTE | DISCO P DESVASTE | PZA | 0.400000 | $31.25 | $12.50 |
| PRIM. ANTICORROSIVO | PRIMARIO ANTICORROSIVO | LT | 1.500000 | $47.00 | $70.50 |
| THINER | THINER | LT | 1.700000 | $12.00 | $20.40 |
| ESMALTE ALKIDALICO | ESMALTE ALKIDALICO SHERWIN WILLIAMS | LT | 1.800000 | $67.00 | $120.60 |
| Suma de Material | $6,284.50 | ||||
| Mano de Obra | |||||
| CUAD OC PAIL | CUAD. 1 OF. PAILERO + 1 AYUDANTE. | jor | 3.000000 | $783.80 | $2,351.40 |
| CUAD OC PINT | CUAD. 1 OF. PINTORr + 2 AYUDANTES. | jor | 2.000000 | $1,086.03 | $2,172.06 |
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 2.000000 | $764.36 | $1,528.72 |
| Suma de Mano de Obra | $6,052.18 | ||||
| Equipo | |||||
| SOLDADURA MILLLER | Soldadora Miller Dimension Mod. 652 | hora | 0.100000 | $29.58 | $2.96 |
| ESMERILADORA | Esmeriladora | HR | 0.100000 | $10.06 | $1.01 |
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 0.100000 | $0.59 | $0.06 |
| Suma de Equipo | $4.02 | ||||
| Costo Directo | $12,340.70 |