| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 030532 | FABRICACION Y MONTAJE HASTA 20 METROS DE ALTURA DE ESTRUCTURA METALICA CON PERFILES MON-TEN PTR | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 0128-02 | PERFILES MON-TEN 4" | TON | 0.001100 | $6,180.00 | $6.80 |
| 0128-03 | ANGULO Y SOLERA COMERCIAL A-36 | TON | 0.000100 | $5,866.38 | $0.59 |
| 1551-30 | SOLDADURA E-6013 DE 1/8" | KG | 0.030000 | $26.91 | $0.81 |
| 2600-95 | PINTURA ANTICORROSIVA ( PRIMER ) COMEX | LT | 0.007000 | $26.44 | $0.19 |
| 2000-62 | GRUA, PLUMA, POLEAS Y CABLE | R/D | 0.003300 | $209.34 | $0.69 |
| 0308-25 | TORRE DE TRABAJO DE 12 M DE ALTURA CON RUEDAS | R/D | 0.003300 | $61.00 | $0.20 |
| Suma de Material | $9.28 | ||||
| Mano de Obra | |||||
| 02-0810 | CUADRILLA No 81 ( 1 SOLDADOR CALIFICADO + 2 SOLDADORES + 3 AYUDANTES ) | JOR | 0.014200 | $1,781.62 | $25.30 |
| Suma de Mano de Obra | $25.30 | ||||
| Costo Directo | $34.58 |