| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 452 | DENTELLON DE CONCRETO DE 45 X 40 X 20 CMS. ARMADO CON 4 VR #3 Y #3@25 CMS. | ML |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| DESMOLDANTE | DESMOLDANTE | LT | 0.500000 | $13.80 | $6.90 |
| ACE#3 | ACERO DE REFUERZO DE 3/8" #3 f`y = 4200 kg/ml | KG | 3.280000 | $8.20 | $26.90 |
| ACE#4 | ACERO DE REFUERZO De 1/2" #4 f`y = 4200 kg/ml | kg | 4.100000 | $8.20 | $33.62 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.300000 | $12.00 | $3.60 |
| CONC.PREMEZ.F-C=200 | CONCRETO PREMEZCLADO F'C= 200 KG/CM2 | M3 | 0.093000 | $991.90 | $92.25 |
| Suma de Material | $163.26 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBA脩IL + 1 PEON | jor | 0.100000 | $764.36 | $76.44 |
| Suma de Mano de Obra | $76.44 | ||||
| Auxiliar | |||||
| BAS -CIMMET | CIMBRA METALICA DE 40 CMS DE ALTURA | ml | 0.030530 | $557.32 | $17.01 |
| Suma de Auxiliar | $17.01 | ||||
| Costo Directo | $256.71 |