| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 7:02(A) | COLUMNA (TIPO C-H1)SECCION= 40 X 40 CM, CONCRETO HECHO EN OBRA F'C=250 KG/CM2-3/4", CIMBRA 4 CARAS APARENTE REFORZADO CON 8VARILLAS DE 1" CON. ESTRIBOS DE 3/8" A/C 20 CM GALV. POR IMNERSION EN CALIENTE. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRAPLAY | CIMBRAPLAY 16 MM | m2 | 0.530000 | $69.00 | $36.57 |
| MADERA DE PINO | MADERA PINO 3a. | pt | 3.250000 | $5.90 | $19.18 |
| CLAVO | CLAVO | KG | 0.300000 | $13.50 | $4.05 |
| DIESEL | DIESEL | LT | 0.500000 | $4.20 | $2.10 |
| GALVANIZADO POR INME | KG | 42.640000 | $3.00 | $127.92 | |
| AGUA | M3 | 0.125000 | $45.00 | $5.63 | |
| Suma de Material | $195.44 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-04 | (1 OFICIAL CARPINTERO OBRA NEGRA + 1 AYUDANTE) | jor | 0.120000 | $576.23 | $69.15 |
| Suma de Mano de Obra | $69.15 | ||||
| Concepto | |||||
| CE-03-03 | ACERO DE REFUERZO DEL No. 5 EN CIMENTACION | TON | 0.041000 | $13,029.10 | $534.19 |
| CE-05-02 | F'c= 250 KG/CM2, AGREGADO MAXIMO DE 19 MM., CLASE I | M3 | 0.168000 | $1,181.25 | $198.45 |
| Suma de Concepto | $732.64 | ||||
| Costo Directo | $997.23 |