| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EC.40A | SUMINISTRO Y COLOCACIÓN DE CONCRETO PREMEZCLADO F'C= 250 KG/CM² T.M. 19 MM. NORMAL REV. 12-14, BOMBEADO CON IMPERMEABILIZANTE INTEGRAL PARA TRABES DE ENTREPISO, LOSAS Y COLUMNAS. COMPRENDE: VIBRADO. INCLUYE: MATERIALES DE CONSUMO, MANO DE OBRA, HERRAMIENTAS Y DEMÁS CARGOS CORRESPONDIENTES POR UNIDAD DE OBRA TERMINADA | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-09 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2 | M3** | 1.050000 | $725.00 | $761.25 |
| CONCRETO PRE-09 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2 | M3** | 1.050000 | $725.00 | $761.25 |
| CONCRETO PRE-09 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2 | M3** | 1.050000 | $725.00 | $761.25 |
| CONCRETO PRE-09 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2 | M3** | 1.050000 | $725.00 | $761.25 |
| CONCRETO PRE-09 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2 | M3** | 1.050000 | $725.00 | $761.25 |
| CONCRETO PRE-09 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2 | M3** | 1.050000 | $725.00 | $761.25 |
| CONCRETO-15 | BOMBA PARA CONCRETO | M3** | 1.050000 | $115.00 | $120.75 |
| CONCRETO-15 | BOMBA PARA CONCRETO | M3** | 1.050000 | $115.00 | $120.75 |
| CONCRETO-15 | BOMBA PARA CONCRETO | M3** | 1.050000 | $115.00 | $120.75 |
| CONCRETO-15 | BOMBA PARA CONCRETO | M3** | 1.050000 | $115.00 | $120.75 |
| CONCRETO-15 | BOMBA PARA CONCRETO | M3** | 1.050000 | $115.00 | $120.75 |
| CONCRETO-15 | BOMBA PARA CONCRETO | M3** | 1.050000 | $115.00 | $120.75 |
| CONCRETO-FESTER-01 | FESTEGRAL | KG | 14.000000 | $8.83 | $123.62 |
| CONCRETO-FESTER-01 | FESTEGRAL | KG | 14.000000 | $8.83 | $123.62 |
| CONCRETO-FESTER-01 | FESTEGRAL | KG | 14.000000 | $8.83 | $123.62 |
| CONCRETO-FESTER-01 | FESTEGRAL | KG | 14.000000 | $8.83 | $123.62 |
| CONCRETO-FESTER-01 | FESTEGRAL | KG | 14.000000 | $8.83 | $123.62 |
| CONCRETO-FESTER-01 | FESTEGRAL | KG | 14.000000 | $8.83 | $123.62 |
| Suma de Material | $6,033.72 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.100000 | $1,251.29 | $125.13 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.100000 | $1,251.29 | $125.13 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.100000 | $1,251.29 | $125.13 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.100000 | $1,251.29 | $125.13 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.100000 | $1,251.29 | $125.13 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.100000 | $1,251.29 | $125.13 |
| Suma de Mano de Obra | $750.77 | ||||
| Auxiliar | |||||
| ANDAMIO | ANDAMIO metalicos | DIA | 0.100000 | $17.33 | $1.73 |
| ANDAMIO | ANDAMIO metalicos | DIA | 0.100000 | $17.33 | $1.73 |
| ANDAMIO | ANDAMIO metalicos | DIA | 0.100000 | $17.33 | $1.73 |
| ANDAMIO | ANDAMIO metalicos | DIA | 0.100000 | $17.33 | $1.73 |
| ANDAMIO | ANDAMIO metalicos | DIA | 0.100000 | $17.33 | $1.73 |
| ANDAMIO | ANDAMIO metalicos | DIA | 0.100000 | $17.33 | $1.73 |
| Suma de Auxiliar | $10.40 | ||||
| Costo Directo | $6,794.89 |