| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IE.360 | ALIMENTACION ELECTRICA INC. DUCTO, CABLE CAL.1/0, 2 Y MANO DE OBRA | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| POLIDUCTO 51 MM | POLIDUCTO 51 MM | ML | 1.050000 | $9.50 | $9.98 |
| CLAVO 1 1/2" | CLAVO 1 1/2" | kg | 0.062500 | $12.20 | $0.76 |
| RAFIA | RAFIA | ml | 0.150000 | $1.20 | $0.18 |
| GUIA ACERADA | GUIA ACERADA ROLLO 60 MTRS | PZA | 0.025000 | $451.05 | $11.28 |
| CUERDA NYLON 3/4" | CUERDA NYLON 3/4" | MT | 1.050000 | $25.41 | $26.68 |
| GUIA ALAMBRE NO 14 | GUIA ALAMBRE NO 14 | ml | 0.500000 | $0.50 | $0.25 |
| CINTA AISLAR | CINTA AISLAR | PZA | 0.200000 | $10.00 | $2.00 |
| CABLE THWLS CAL. 1/0 | CABLE THWLS CAL. 1/0 | ML | 3.450000 | $99.02 | $341.62 |
| CABLE THWLS CAL. 2 | CABLE THWLS CAL. 2 | ML | 1.250000 | $63.48 | $79.35 |
| Suma de Material | $472.09 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | JOR | 0.035714 | $650.39 | $23.23 |
| Suma de Mano de Obra | $23.23 | ||||
| Costo Directo | $495.32 |