| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IECN-009 | TABLERO DE DISTRIBUCION FRENTE SOBREPONER CON INTERRUPTOR PRINCIPAL DE 150 AMP CAT NQOD424AB22S INCLUIR KIT DE TIERRAS, ARMADO DEL TABLERO, BALANCEO, PEINADO DE CABLEADO Y TODO LO NECESARIO PARA SU CORRECTO FUNCIONAMIENTO. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TABNQOD42-4AB22 | TABLERO 42 POLOS , 3F-4H , 220 VOLTS , CATALOGO NQOD42-4AB22 DE SOBREPONER , MARCA SQUARE-D CON INTERRUPTOR PRINCIPAL DE 3 X 150AMP. | PZA | 1.000000 | $2,809.00 | $2,809.00 |
| TAQUETE SCI 3/8" | TAQUETE TIPO SCI DE 3/8" CLEVIS | PZA | 4.000000 | $4.03 | $16.12 |
| TORN-G3/8X1 | TORNILLO GALVANIZADO DE 3/8" X 1" DE LARGO | PZA | 4.000000 | $1.50 | $6.00 |
| ROLDANA PLANA 3/8" | ROLDANA PLANA DE 3/8" DE DIAMETRO | PZA | 4.000000 | $0.50 | $2.00 |
| BROCA 3/8 CONCRETO | BROCA CONCRETO Y FIERRO 3/8" | PZA | 0.062500 | $65.00 | $4.06 |
| CINCHOS 30CM | CINCHOS DE 30CM | PZA | 20.000000 | $0.45 | $9.00 |
| SEGUETAD/STAN | SEGUETA DIENTE STANDARD | PZA | 0.125000 | $8.50 | $1.06 |
| Suma de Material | $2,847.25 | ||||
| Mano de Obra | |||||
| CUAD INST BAJA TENSI | CUADRILLA ELECTRICA DE BAJA TENSION (1Of. Electricista,1 Ayudantes) | JOR | 2.000000 | $881.89 | $1,763.78 |
| Suma de Mano de Obra | $1,763.78 | ||||
| Equipo | |||||
| AMPERIMETRO GANCHO | AMPERIMETRO DE GANCHO MARCA FLUKE | HR | 0.020000 | $0.01 | $0.00 |
| TALADRO ROTOMARTILLO | TALADRO ROTOMARTILLO MCA. DWALT 5/8"-1/2" | HR | 0.250000 | $18.92 | $4.73 |
| Suma de Equipo | $4.73 | ||||
| Costo Directo | $4,615.76 |