| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| HERRERIA-01 | SUMINISTRO Y COLOCACION DE ESTRUCTURA PARA SOPORTAR PRETIL A BASE DE PERFIL TUBULAR GALVANIZADO ZR-400,CAL 20, DE 100MM X 38 MM ,INCLUYE: METRIALES, EQUIPO, HERRAMIENTA Y MANO DE OBRA.(P.U.O.T.) | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| HERRERIA-006 | PERFIL TUBULAR GALVANIZADO ZR-400,CAL 20, | kg | 1.050000 | $11.26 | $11.82 |
| HERRERIA-004 | SOLDADURA E-6013 | KG | 0.001000 | $17.21 | $0.02 |
| PINTURA-05 | PRIMARIO ANTICORROSIVO | LT | 0.002000 | $37.66 | $0.08 |
| PINTURA-03 | PINTURA DE ESMALTE COMEX 100 | LT | 0.003000 | $47.18 | $0.14 |
| PINTURA-06 | THINNER | LT. | 0.001000 | $13.38 | $0.01 |
| HERRERIA-002 | DISCO P/DESBASTE | PZA | 0.000500 | $38.00 | $0.02 |
| COMBUSTIBLE 07 | OXIGENO | M3 | 0.002000 | $29.00 | $0.06 |
| COMBUSTIBLE 08 | ACETILENO | M3 | 0.002000 | $65.00 | $0.13 |
| Suma de Material | $12.28 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 22 | (1 OF. Herrero+1 AYUD.) | Jor | 0.050000 | $426.72 | $21.34 |
| CUADRILLA NO. 18 | (1 Of. Pintor +2 Ayudante). | Jor | 0.002000 | $678.93 | $1.36 |
| CUADRILLA N° 343 EM | 1 of.montador + 1 ayudante. | JOR | 0.002000 | $923.94 | $1.85 |
| Suma de Mano de Obra | $24.54 | ||||
| Equipo | |||||
| MAQUINARIA-90 | equipo de oxicorte con 15 ml de manguera | HR | 0.100000 | $6.24 | $0.62 |
| ESMERILADORA | ESMERILADORA | HR | 0.002000 | $19.43 | $0.04 |
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 0.005000 | $0.59 | $0.00 |
| Suma de Equipo | $0.67 | ||||
| Costo Directo | $37.49 |