| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMBRA MURO | CIMBRA PARA MURO DE CONCRETO CICLOPEO | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SCT-MAT-FERR-01 | Clavo de 2½" a 4" | kg | 0.050000 | $20.00 | $1.00 |
| SCT-MAT-MAD-02 | Triplay de 1.22 x 2.44 m 16 mm 1 cara | m2 | 0.200000 | $107.38 | $21.48 |
| SCT-MAT-MAD-01 | Barrote 1 1/2 x 4 x 8 | pt | 2.000000 | $12.00 | $24.00 |
| SCT-MAT-MAD-04 | Polin 3 1/2 x3 1/2 x8 1/4 | pt | 2.000000 | $11.00 | $22.00 |
| SCT-MAT-COMB-01 | Diesel | lt | 1.000000 | $8.70 | $8.70 |
| Suma de Material | $77.18 | ||||
| Mano de Obra | |||||
| SCT-CUA-08 | Cuadrilla (1 Carpintero + 1 Ayudante) | Jor | 0.100000 | $928.57 | $92.86 |
| Suma de Mano de Obra | $92.86 | ||||
| Herramienta | |||||
| SCT-HERR-01 | Herramienta menor | (%)mo | 0.020000 | $92.86 | $1.86 |
| SCT-HERR-02 | Seguridad industrial | (%)mo | 0.020000 | $92.86 | $1.86 |
| Suma de Herramienta | $3.72 | ||||
| Costo Directo | $173.76 |