| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 22.00 | SUMINISTRO Y COLOCACION DE MURO DE BLOCK HUECO DE CONCRETO TIPO INTERMEDIO (11 KG/BLOQUE) DE 12 X 20 X 40 CMS ASENTADO CON MORTERO CEMENTO ARENA PROP: 1:4 CON JUNTA HORIZONTALDE 1 CMDE ESPESOR REFUERZO CON ESCALERILLA DE 1/8" DE DIAMETRO A CADA 3 HILADAS .INCLUYE: MATERIAL, MANO DE OBRA, RECORTES, DESPERDICIOS, ANDAMIOS, ACARREOS HORIZONTALES Y VERTICALES A CUALQUIER ALTURA, RETIRO DE ESCOMBRO A LUGAR DE TIRO AUTORIZADO POR ASUR, LIMPIEZA DEL ÁREA DE TRABAJO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN, P.U.O.T. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BLOCK | Block hueco 15 x 20 x 40 | mill | 0.013750 | $4,500.00 | $61.88 |
| BLOCK | Block hueco 15 x 20 x 40 | mill | 0.013750 | $4,500.00 | $61.88 |
| BLOCK | Block hueco 15 x 20 x 40 | mill | 0.013750 | $4,500.00 | $61.88 |
| BLOCK | Block hueco 15 x 20 x 40 | mill | 0.013750 | $4,500.00 | $61.88 |
| DISCO DE DIAMANTE 7" | DISCO DE DIAMANTE 7" | PZA | 0.010000 | $388.00 | $3.88 |
| DISCO DE DIAMANTE 7" | DISCO DE DIAMANTE 7" | PZA | 0.010000 | $388.00 | $3.88 |
| DISCO DE DIAMANTE 7" | DISCO DE DIAMANTE 7" | PZA | 0.010000 | $388.00 | $3.88 |
| DISCO DE DIAMANTE 7" | DISCO DE DIAMANTE 7" | PZA | 0.010000 | $388.00 | $3.88 |
| ESCARELILLA | Escalerilla de 1/8" DE DIAMETRO | ML | 1.660000 | $22.00 | $36.52 |
| ESCARELILLA | Escalerilla de 1/8" DE DIAMETRO | ML | 1.660000 | $22.00 | $36.52 |
| ESCARELILLA | Escalerilla de 1/8" DE DIAMETRO | ML | 1.660000 | $22.00 | $36.52 |
| ESCARELILLA | Escalerilla de 1/8" DE DIAMETRO | ML | 1.660000 | $22.00 | $36.52 |
| Suma de Material | $409.10 | ||||
| Mano de Obra | |||||
| CALB21 | (1 Of. Albanil + 1 Peón) | JOR | 0.125000 | $1,143.98 | $143.00 |
| CALB21 | (1 Of. Albanil + 1 Peón) | JOR | 0.125000 | $1,143.98 | $143.00 |
| CALB21 | (1 Of. Albanil + 1 Peón) | JOR | 0.125000 | $1,143.98 | $143.00 |
| CALB21 | (1 Of. Albanil + 1 Peón) | JOR | 0.125000 | $1,143.98 | $143.00 |
| 00-0010 | Peón | jor | 0.055556 | $354.61 | $19.70 |
| 00-0010 | Peón | jor | 0.055556 | $354.61 | $19.70 |
| 00-0010 | Peón | jor | 0.055556 | $354.61 | $19.70 |
| 00-0010 | Peón | jor | 0.055556 | $354.61 | $19.70 |
| Suma de Mano de Obra | $650.79 | ||||
| Equipo | |||||
| ESMERILADORA | Esmeriladora | HR | 0.055556 | $2.58 | $0.14 |
| ESMERILADORA | Esmeriladora | HR | 0.055556 | $2.58 | $0.14 |
| ESMERILADORA | Esmeriladora | HR | 0.055556 | $2.58 | $0.14 |
| ESMERILADORA | Esmeriladora | HR | 0.055556 | $2.58 | $0.14 |
| Suma de Equipo | $0.57 | ||||
| Auxiliar | |||||
| MEZ0003 | Mortero cemento - arena gruesa 1 : 4 | m3 | 0.015000 | $1,069.46 | $16.04 |
| MEZ0003 | Mortero cemento - arena gruesa 1 : 4 | m3 | 0.015000 | $1,069.46 | $16.04 |
| MEZ0003 | Mortero cemento - arena gruesa 1 : 4 | m3 | 0.015000 | $1,069.46 | $16.04 |
| MEZ0003 | Mortero cemento - arena gruesa 1 : 4 | m3 | 0.015000 | $1,069.46 | $16.04 |
| AND006 | Andamio de acero tubular de 4.00m. de altura con ruedas y base de tablones de madera. | r/d | 0.083333 | $66.01 | $5.50 |
| AND006 | Andamio de acero tubular de 4.00m. de altura con ruedas y base de tablones de madera. | r/d | 0.083333 | $66.01 | $5.50 |
| AND006 | Andamio de acero tubular de 4.00m. de altura con ruedas y base de tablones de madera. | r/d | 0.083333 | $66.01 | $5.50 |
| AND006 | Andamio de acero tubular de 4.00m. de altura con ruedas y base de tablones de madera. | r/d | 0.083333 | $66.01 | $5.50 |
| Suma de Auxiliar | $86.17 | ||||
| Costo Directo | $1,146.64 |