| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-03 | MURO DE CONCRETO F'C 250 KG/CM2 DE 15 CMS DE ESPESOR, ARMADO CON VARILLAS No.3 @ 15 CMS., INC. MATERIALES, MANO DE OBRA, HERRAMIENTA, EQUIPO Y TODO LO NECESARIOA PARA SU CORRECTA EJECUCIÓN. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO VARIOS DIAM. | ACERO REF.VARIAS DIM | KG | 13.360000 | $8.50 | $113.56 |
| ALAMBRE RECOC 18 | ALAMBRE RECOCIDO # 18 | KG | 5.000000 | $14.87 | $74.35 |
| CONC.PREMEZ.F´C=300 | Concreto Premezclado F'c=300 Kg/cm2 A.M. 3/4" rev 13-14 | M3 | 0.200000 | $820.00 | $164.00 |
| AGUA | agua | M3 | 0.050000 | $40.00 | $2.00 |
| POLIN 3.5" X 3.5" | MADERA DE PINO DE 3A. EN POLIN DE 3.5" X 3.5" | PT | 0.150000 | $7.50 | $1.13 |
| BARROTE 1.5" X 3.5" | MADERA DE PINO DE 3A. EN BARROTE DE 1.5" X 3.5" | PT | 0.150000 | $5.60 | $0.84 |
| CIMBRAPLAY 16 MM | cimbraplay de 16 mm | M2 | 0.333000 | $90.00 | $29.97 |
| CLAVOS | VARIAS MEDIDAS NORMAL .004KG/PZA PROM. | KG | 0.050000 | $17.50 | $0.88 |
| DIESEL | diesel pemex | Lt | 0.500000 | $6.50 | $3.25 |
| Suma de Material | $389.97 | ||||
| Mano de Obra | |||||
| CUAD 18 | Cuadrilla No. 18 ( 1 Of. Fierrero + 1Ayudante). | jor | 0.008333 | $799.88 | $6.67 |
| CUAD 05 | ( 1 ALBAÑIL + 5 PEONES ) | jor | 0.008333 | $2,105.73 | $17.55 |
| 2CUA CARPINTERO 2 | (1 Oficial carpintero de obra negra + 1 ayte.) | JOR | 0.125000 | $815.26 | $101.91 |
| Suma de Mano de Obra | $126.12 | ||||
| Equipo | |||||
| BOMBA PLUMA | Bomba pluma para concreto con diámetro hasta 4" (102mm) | M3 | 0.200000 | $140.00 | $28.00 |
| VIBRADOR P/CONCRETO | Vibrador para concreto Mot. Kohler 4 H.Con operador. | HR | 0.050000 | $56.24 | $2.81 |
| Suma de Equipo | $30.81 | ||||
| Costo Directo | $546.90 |